Reconstruction Hypernova OPTIMA – Košice – Stage 1, will consist mainly of demolition works and floor renovation.
Project manager: Ing. Albert Vavrek
Beginning: 05.05.2017
End: 14.07.2017
Work description:
05/06/2017
Dismantling of cooling, water, electricity, lighting, 1st layer of SHZ, EPS, ZODT and other suspended distributions, floor demolition in the scope of the revised PD, removal of base layers with disposal to landfill.
16/06/2017
Excavations were completed, land taken, pressure plans were executed, and we began to load and compact the underlying gravel layers
13/07/2017
Removal of the remaining installations hanging in the horizontal plane under the roof hull construction is carried out.
Welded plastic pipes are welded.
Currently, trenches and pit excavations are carried out for sewerage piping and sewerage inspection shafts.
In the whole of the floor plan of the raised and reconstructed floor, compacted embankments are made up to the level of the lower surface of the reinforced concrete slab.
Completed and handed over to the investor, on day 25.08.2017.