Construction: Slovnaft petrol station – car wash reconstruction
Location: Slovnaft petrol station Modra
Construction commencement: 10/2019
Construction completion: 11/2019
Construction type: Car wash
Activity: General contractor
Investor: SLOVNAFT, a.s.
Project management: Ing. Tomáš Krutek
Description of works:
The project deals with the reconstruction: maintenance works and a change of the car wash technology. The object of the reconstruction: new paint on the walls and the ceiling, an installation of a steel construction for the lower jets, a change of the original equipment of the car wash line, a change of the lighting, an addition of DEVI bands, a change of the radiators, cleaning of the ceramic floor, wall adverts, an installation of an artificial ventilation, a new datamat with a base, removing of the original RVI element – a yellow band and an installation of a new sign „Autoumyváreň“ (car wash), newly painted facade, a change of both section gates.