Construction: MOL petrol station – Praha, Štěrboholy (out) – Fresh Corner
Location: Praha, Štěrboholská spojka
Construction commencement: June 2018
Construction completion: July 2018
Construction type: petrol station
Activity: General contractor
Investor: MOL Česká republika, s.r.o.
Project manager: Ing. Daniel Rimel
Scope of work:
Complete layout adjustment – demolition and construction of SDK walls, including the background, new sewer and water distribution. Change of ceramic cladding, paving and the equipment. Complete change of the wiring including the lighting. Complete change of the ventilation and the air-conditioning. Dismantling of the sheet facade and installation of an insulation system. New waterproofing of the roof. Installation of a cobblestone terrace.