Project: The reduction of energy consumption during the operation of the Municipal office in Baška
Project manager: Ing. Albert Vavrek
On the 16.05.2017 the company KAMI PROFIT, s.r.o. took over the construction site from the borough Baška. The reconstruction includes mainly the thermal insulation of the walls, the ceiling construction, floors and the horizontal insulation of the floors and the vertical structures against moisture. The scheduled time of works is set for 4 weeks.
Workflow: to 16.06.2017 – finishing works in progress – internal coating, painting, floating floor and photovoltaics.
Construction finished and submitted to investor – 06/2017