Construction: OMV petrol station reconstruction Pezinok
Location: Obchodná street 22, Pezinok
Construction commencement: 03/2020
Construction completion: 05/2020
Construction type: Petrol stations
Activity: General contractor
Investor and purchaser: OMV Slovensko s.r.o.
Project manager: Ing. Peter Podmanický, Ing. Minh Nguyen Tien, Phd.
Description of works:
An extension of the shop area. A complete layout adjustment including the background, a change of cladding, paving and the equipment, new plasterboard ceilings, painting of the space, a construction preparation for the change of the RVI elements, the lighting, a change of the furniture, facade works. A new steel roof, installation of a new tank, relocation of the LPG dispenser, a new area for storing material and a new permanent traffic marking.