Construction: Reconstruction and modernisation of the secondary school of information technologies, 30 Tajovského street, Banská Bystrica
Location: 30 Tajovského street, Banská Bystrica
Construction commencement: August 2020
Construction completion: August 2021
Construction type: Reconstruction
Activity: General contractor
Investor and purchaser: Secondary school of information technologies Banská Bystrica, Banská Bystrica self governing region
Project manager: Ing. Andrej Žiška
Description of works:
Reconstruction and modernisation of the dormitory’s interior, the classrooms, corridors, the library and the workshops. Elevator shaft extension, a change of the elevator. New windows and doors. Reconstruction of the main entrance.