Construction: Slovnaft – Reinforced area
Location: Vlčie hrdlo 1, Bratislava – Slovnaft a.s. grounds
Construction commencement: 01/2020
Construction completion: 03/2020
Construction type: Road construction
Activity: General contractor
Investor and purchaser: SLOVNAFT, a.s.
Project manager: Miroslav Pavlák
Description of works:
Renovation of the original objects in a volume of 3500 m3
Drainage of the reinforced areas.
The construction of a reinforced area made of CB III concrete with a broom surface finish of 1800 m2.
Traffic connection to the existing infrastructure.