Construction: Energy savings VI. Stage – SOUS Opava
Location: Boženy Němcové 2309/22, 746 01 Opava
Start of construction: 10/2025
Completion of construction: 1/2027
Type of construction: School building – civic amenities with a built-up area of up to 2,000 m²
Activity: General contractor
Investor and client: Moravian-Silesian Region
Project manager: Bc. Jaroslav Svrček
Price of the work: CZK 93,578,054 + VAT
Description of activity: The project “Energy Savings Phase VI – SOUS Opava” involves the comprehensive renovation of school buildings with the aim of reducing their energy consumption and increasing comfort for students and school staff.
The work carried out includes insulation of facades and roofs, replacement of windows and doors, reconstruction of heating, installation of ventilation and installation of a photovoltaic system on the roof of pavilion A.
The project also includes a complete reconstruction of the school’s high-rise building and modernization of technical equipment.
The aim is to create a modern, energy-efficient, and environmentally friendly school environment that will contribute to the sustainable operation of the school and improve the quality of teaching and user comfort.